Fond du Lac: Construction on WIS 23, County VV due to start Monday, what to expect


FOND DU LAC, Wis. (WFRV) – Residents of Fond du Lac should expect to experience traffic impacts along Pioneer Road in Fond du Lac starting Monday.

According to the Wisconsin Department of Transportation (WisDOT), on June 6, crews will begin construction of the WIS 23 and County VV (Pioneer Road) intersection.

WisDOT officials say their goal is to improve safety at the intersection of US 45/WIS 23 and County VV (Pioneer Road) by reducing conflict points.

Crews plan to accomplish this goal by constructing split left-turn lanes along US 45/WIS 23, as well as a dedicated right-turn lane along US 45/WIS 23 toward west.

Construction is expected to be completed by mid-August 2022. Officials confirm that WIS 23 will remain open to traffic except for a maximum three-day closure in July.

More information on project dates and traffic impacts can be found below.

Traffic impacts

  • Step 1: June 6 to July 21
    • County VV to the north will be closed to traffic with a detour.
  • 2nd step : July 21 to July 23
    • County VV to the north will be closed to traffic with a detour.
    • US 45/WIS 23 will be closed to traffic with a detour. Maximum 3 working days.
  • Step 3: July 23 to August 9
    • County VV to the north will be closed to traffic with a detour.